|
|
|
|
|
|
Meeting Date:
|
8/24/2015 - 5:30 PM
|
Category:
|
Consent Agenda
|
Type:
|
Action
|
Subject:
|
13.14 (Item #17) Final Additive Change Order for Bid #1718/Contract 932, Concrete Repair at Hidden Valley Elementary
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On June 22, 2015, the Board of Education ratified the Award of Bid for Bid #1718/Contract C-932 to R & S Construction Management, Inc., for a total amount of $93,422.00. As a result of removing the concrete stage and additional drainage, a change order of $15,000.00 is necessary. The revised project total is $108.422.00.
|
Funding:
|
6210 Facilities & Capital Outlay
|
Fiscal Impact
:
|
$15,000.00
|
Recommendation:
|
Approve the additive change order to Bid 1718/Contract 932 in the amount of $15,000.00.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Laura Warner - Administrative Secretary
|
|
Signed By:
|
|
Jeff McDaniel - Executive Director of Operations
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Moved, Member seconded to approve the Original motion 'Approve all Consent Agenda items.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Barbara Oaks | Yes | Cheryl Hansen | Yes | Linda Mayo | Yes | Brian Lawrence | Yes | Debra Mason | Yes | |
|
|
|
|
|
|