Subject: 13.14 (Item #17) Final Additive Change Order for Bid #1718/Contract 932, Concrete Repair at Hidden Valley Elementary
LCAP (Local Control Accountability Plan) Goal:
Strategic Initiative 5.3 Optimal Operations and Infrastructure
Ensure that our facilities and infrastructure support and enhance student learning and safety.
Policy:
Enclosure
File Attachment:
Summary: On June 22, 2015, the Board of Education ratified the Award of Bid for Bid #1718/Contract C-932 to R & S Construction Management, Inc., for a total amount of $93,422.00. As a result of removing the concrete stage and additional drainage, a change order of $15,000.00 is necessary. The revised project total is $108.422.00.
Funding: 6210 Facilities & Capital Outlay
Fiscal Impact $15,000.00
Recommendation: Approve the additive change order to Bid 1718/Contract 932 in the amount of $15,000.00.
Approvals:
Recommended By:
Signed By:
Laura Warner - Administrative Secretary
Signed By:
Jeff McDaniel - Executive Director of Operations
Signed By:
Dr. Nellie Meyer - Superintendent
Vote Results:

Original Motion
Member Moved, Member seconded to approve the Original motion 'Approve all Consent Agenda items.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Barbara Oaks     Yes
Cheryl Hansen     Yes
Linda Mayo     Yes
Brian Lawrence     Yes
Debra Mason     Yes