|
|
|
|
|
|
Meeting Date:
|
3/23/2015 - 7:00 PM
|
Category:
|
Business/Action Items
|
Type:
|
Action
|
Subject:
|
19.11 Final Change Order 1627-001 (DEDUCTIVE) to Taber Construction, Inc. for Lease/Leaseback #1627 – Security System Replacement.
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On November 13, 2013 the Board of Education awarded Lease/Leaseback Agreement #1627 to Taber Construction, Inc. for a Guaranteed Maximum Project Cost of $8,883,760.49 for the provision of all tools, materials, labor and equipment necessary to complete District-wide security system upgrades at all sites. As a result of unused contract contingency, a single, final deductive change order in the amount of <$208,254.00> is necessary. This single, final change order will result in a final revised contract value of $8,675,506.49 and represents a decrease of 2.34% to original contract value.
|
Funding:
|
2010 Measure C
|
Fiscal Impact
:
|
<$208,254.00> DEDUCTIVE
|
Recommendation:
|
Approve Final Change Order 1627-001 (DEDUCTIVE) to Taber Construction, Inc. for Lease/Leaseback #1627 – Security System Replacement.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
John Willford - Assistant Program Manager
|
|
Signed By:
|
|
Tim Cody - Program Manager
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
New Motion | Member Linda Mayo Moved, Member Barbara Oaks seconded to approve the New motion 'Approve final Change Order 1627-001 (DEDUCTIVE) to Taber Construction, Inc. for Lease/Leaseback #1627 – security system replacement.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Barbara Oaks | Yes | Debra Mason | Yes | |
|
|
|
|
|
|