Subject:
|
13.30 (Item #32) Notice of Completion for RFQ 1722/Contract C-937: Paving and Grading of Northgate High School
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
RFQ 1722 was called to provide paving and grading at Northgate High School. The lowest responsible bidder was R & M Paving Contractors, Inc. for the bid award amount of $124,272.00. The scope of work includes, but is not limited to: all labor, materials and asphalt paving including running of utility conduit. There was an additive change order on this project in the amount of $7,546.00, services for this project have been satisfactorily completed for a total expenditure of $131,728.00.
|
Funding:
|
3614: Redevelopment Funds-Secondary Capital Outlay
|
Fiscal Impact
:
|
$131,728.00
|
Recommendation:
|
Approve the Notice of Completion of RFQ 1722/ Contract C-937.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Jennifer Woodhall - Administrative Secretary II
|
|
Signed By:
|
|
Jeff McDaniel - Executive Director of Operations
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Moved, Member seconded to approve the Original motion 'Approve all Consent Agenda items.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Cheryl Hansen | Yes | Barbara Oaks | Yes | Debra Mason | Yes | Brian Lawrence | Yes | |
|
|
|
|
|
|