Subject: 13.18 Review and Potential Approval of Final Change Order for CUPCCAA Bid #1851 New Accessible Parking and Bleacher Access at Mt. Diablo High School
LCAP (Local Control Accountability Plan) Goal:
Goal 1:
All students will receive a high quality education in a safe and welcoming environment with equitable and high expectations, access to technology, and instruction in the California State Standards that prepare them for college and career.
Policy:
Enclosure Bid 1851 Final Change Order
Bid 1851 Change Order Summary
Bid 1851 Back Up
File Attachment:
Bid 1851 Final Change Order.pdf
Bid 1851 Change Order Summary Log.pdf
Bid 1851 Back Up.pdf
Summary: Background: The attached change order summary list and backup documents describe (1) scope changes to CUPCCAA Bid #1851 New Accessible Parking and Bleacher Access at Mt. Diablo High School. The (1) scope changes involve (1) separate Change Order Requests (COR’s). The MDUSD Construction Manager and District Administration have reviewed each request. The work has been authorized for all aforementioned COR’s.

Current Consideration: Ratification of the (1) COR’s authorization of the addition of the approved amounts to the original contract. The contractor may bill for the additional work once approved by the board as the scope has been verified as complete. The added scope of work was presented as a Owner Directive to resolve drainage issues and protection of the synthetic track that would be caused by an unidentified drain basin that was discovered during construction that was not included in the district as builts. The discovery of this storm basin that was uncovered during the project scope proved the storm drain system was not directing water collected in the manner our documents showed.

Fiscal Impact: The total cost of the (1) COR’s is an increase of $12,100.00. This is a 9.97% increase to the original contract. This project is funded by the Measure C General Obligation Bond and no additional funding is necessary.
Funding: Measure C
Fiscal Impact Increase of $12,100.00 to bring the total to $133,500.00.
(Total amount is within the 20/21 budget allocation)
Recommendation: Move to approve the Final Change Order for CUPCCAA Bid #1851 New Accessible Parking and Bleacher Access at Mt. Diablo High School
Approvals:
Recommended By:
Signed By:
Melanie Koslow - Director of Maintenance and Operations
Signed By:
Elizabeth McClanahan - Director of Purchasing and Warehouse
Signed By:
Mika Arbelbide - Director of Fiscal Services
Signed By:
Dr. Lisa Gonzales - Chief Business Officer
Signed By:
Dr. Adam Clark - Superintendent