18.15 Intermediate Change Order 1782-001 for Contract #1782/C-958-18 with Goodland Landscape, Inc., for Concord High School Athletic Fields Improvements Project #1782
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On May 22, 2017 the Board of Education awarded contract C958 Project #1782 to Goodland Landscape, Inc. for $5,150,000.00 for the provision of all tools, materials, labor and equipment necessary to complete Concord High School Athletic Fields Improvements according to the plans and specifications. This Intermediate Change Order for unforeseen conditions, electrical work, fencing and concrete changes will result in the addition of $253,931.44 to the original contract. This intermediate change order will result in a revised contract value of $5,403,931.44 and represents an increase of 4.93% to the original contract value.
|
Funding:
|
Measure A funds
|
Fiscal Impact
:
|
$253,931.44
|
Recommendation:
|
Approve the Intermediate Change Order 1782-001 for Contract #1782/C-958-18 with Goodland Landscape, Inc. for Concord High School Athletic Fields Improvements Project #1782.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
John Willford - Assistant Program Manager
|
|
Signed By:
|
|
Brad Hunter - Director
|
|
Signed By:
|
|
Nance Juner - Director of Fiscal Services
|
|
Signed By:
|
|
Rose Ramos - Chief Business Officer
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
|
|
|
|