|
Meeting Date:
|
|
Category:
|
|
Type:
|
|
Subject:
|
13.27 (Item #28) Deductive Change Order for Bid 1717/Contract C-936 |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
On August 10, 2015, the Board of Education ratified the Award of Bid 1717 to Best Contracting Services for a total amount of $885,423.00. Due to time constraint the project at Foothill Middle School Gymnasium was cancelled. A deductive change order of $182,060.00 was issued on 8/3/15. The revised project total is $703,363.00. |
|
|
Funding:
|
6210 Facilities & Capital Outlay |
|
|
Recommendation
|
Approve the Deductive Change Order. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Jennifer Woodhall - Administrative Secretary II |
|
Signed By: |
|
Jeff McDaniel - Executive Director of Operations |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Moved, Member seconded to approve the Original motion 'Approve all Consent Agenda items.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Barbara Oaks | Yes | Cheryl Hansen | Yes | Linda Mayo | Yes | Brian Lawrence | Yes | Debra Mason | Yes | |
|
|
|
|
|
|