15.23 (Item #24) Final Deductive Change Order to Innerspace Engineering Corporation Contract #C-941/MDUSD #104047 – Locker Replacement at Northgate High School |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
On August 22, 2016, the Board of Education ratified contract action PO #104047 to Innerspace Engineering Corporation, in the amount of $220,000.00 for the provision of all tools, materials, labor and equipment necessary to facilitate locker replacement at Northgate High School. As a result of District requested scope reduction, a single, final change order (deductive) in the amount of $15,044.84 is necessary. This final change order will result in a contract value of $204,955.16. |
|
|
Funding:
|
|
Recommendation
|
Approve the Final Deductive Change Order to Innerspace Engineering Corporation Contract #C-941/MDUSD #104047 – Locker Replacement at Northgate High School. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Debbie Maher - Sr. Administrative Executive Assistant to the Superintendent |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Linda Mayo Moved, Member Cheryl Hansen seconded to approve the Original motion 'Approve the Final Deductive Change Order to Innerspace Engineering Corporation Contract #C-941/MDUSD #104047 – Locker Replacement at Northgate High School.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Debra Mason | Yes | |
|
|
|
|
|
|