13.29 (Item #31) Final Additive Change Order for RFQ 1722/Contract C-937: Paving and Grading at Northgate High School |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
On August 24, 2015, the Board of Education ratified the Award of RFQ 1722 to R & M Paving Contractors, Inc. for a total amount of $124,272.00. A change order of $7,456.00 was required for an additional conduit run and additional temporary security fencing. The revised project total is $131,728.00. |
|
|
Funding:
|
3614 Redevelopment Funds- Secondary Capital Outlay |
|
|
Recommendation
|
Approve the additive change order to RFQ 1722/ Contract C-937 in the amount of $7,456.00. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Jennifer Woodhall - Administrative Secretary II |
|
Signed By: |
|
Jeff McDaniel - Executive Director of Operations |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Moved, Member seconded to approve the Original motion 'Approve all Consent Agenda items.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Debra Mason | Yes | Linda Mayo | Yes | Cheryl Hansen | Yes | Barbara Oaks | Yes | Brian Lawrence | Yes | |
|
|
|
|
|
|