13.15 (Item #18) Notice of Completion for Bid 1718/Contract 932: Concrete Repair at Hidden Valley Elementary |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
Bid #1718 was called to provide concrete repair at Hidden Valley Elementary School. The lowest responsible, responsive bid was R & S Construction Management, Inc. for the total amount of $93,422.00. The scope of work included, but was not limited to: furnish all necessary labor, materials and equipment to remove and replace damaged concrete at Hidden Valley Elementary. There was an additive change order on this project in the amount of $15,000.00. Work and services for this project have been satisfactorily completed for a total expenditure of $108,422.00. |
|
|
Funding:
|
6210: Facilities & Capital Outlay 3613: Redevelopment Elementary Capital Outlay |
|
|
Recommendation
|
Approve the Notice of Completion of Bid 1718/Contract 932: Concrete Repair at Hidden Valley Elementary School. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Laura Warner - Administrative Secretary |
|
Signed By: |
|
Jeff McDaniel - Executive Director of Operations |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Moved, Member seconded to approve the Original motion 'Approve all Consent Agenda items.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Barbara Oaks | Yes | Linda Mayo | Yes | Debra Mason | Yes | Brian Lawrence | Yes | Cheryl Hansen | Yes | |
|
|
|
|
|
|